[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1267737":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1267737,855,1,"单选题","土质路基的压实原则是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","先轻后重、先静后振、先低后高、先慢后快，轮迹重叠",true,{"key":16,"text":17,"correct":18},"B","先重后轻、先静后振、先低后高、先慢后快，轮迹重叠",false,{"key":20,"text":21,"correct":18},"C","先轻后重、先静后振、先高后低、先慢后快，轮迹重叠",{"key":23,"text":24,"correct":18},"D","先轻后重、先静后振、先低后高、先快后慢，轮迹重叠","土质路基的压实原则：“先轻后重、先静后振、先低后高、先慢后快，轮迹重叠。”压路机最快速度不宜超过4km\u002Fh。",{"id":6,"name":27,"category":28,"favorite":29},"(市政质量)基础知识","建筑工程",0]