[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1267728":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1267728,855,1,"单选题","管道水压主试验阶段要停止注水补压稳定（ ）min后，压力下降不超过所允许压力下降数值时，将试压力降至工作压力并保持恒压30min。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","10",false,{"key":16,"text":17,"correct":18},"B","15",true,{"key":20,"text":21,"correct":14},"C","20",{"key":23,"text":24,"correct":14},"D","25","管道水压主试验阶段要停止注水补压稳定15min后，压力下降不超过所允许压力下降数值时，将试压力降至工作压力并保持恒压30min，进行外观检查若无漏水现象时，水压试验合格。",{"id":6,"name":27,"category":28,"favorite":29},"(市政质量)基础知识","建筑工程",0]