[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1267689":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1267689,855,1,"单选题","某排水管道工程采用承插式混凝土管道，管座为180。，地基为湿陷性黄土，工程沿线范围内有一排高压输电线路。项目部的施工组织设计确定采用机械从上游向下游开挖沟槽，用起重机下管、安管，安管时管道承口背向水流方向。开挖正值雨季，为加快施工进度，机械开挖至槽底高程，由于控制不当，局部超挖达200mm，施工单位自行进行了槽底处理。管座施工采用分层浇筑施工时，对第一次施工的平基表面压光、抹面，达到强度后进行第二次浇筑，为防止挤偏管道，在浇筑混凝土管座时，两侧同时进行，随后项目部对该段管道进行了闭水试验。 该施工单位在开槽埋管施工过程中，下述行为正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","确定采用机械从上游向下游开挖沟槽",true,{"key":16,"text":17,"correct":18},"B","安管时管道承口背向水流方向",false,{"key":20,"text":21,"correct":18},"C","机械开挖至槽底高程",{"key":23,"text":24,"correct":18},"D","局部超挖达200mm，施工单位自行进行了槽底处理","重力流管道的高程和平面位置应严格符合设计要求，一般由下游向上游进行稳管。",{"id":6,"name":27,"category":28,"favorite":29},"(市政质量)基础知识","建筑工程",0]