[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1267679":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1267679,855,1,"单选题","塑料管道回填的时间宜在一昼夜中（ ）的时刻，且回填土中不应含有砾石、冻土块及其他杂硬物体。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","温度最高",false,{"key":16,"text":17,"correct":18},"B","温度最低",true,{"key":20,"text":21,"correct":14},"C","温差最大",{"key":23,"text":24,"correct":14},"D","温差最小","塑料管道回填的时间宜在一昼夜中温度最低的时刻，且回填土中不应含有砾石、冻土-块及其他杂硬物体。",{"id":6,"name":27,"category":28,"favorite":29},"(市政质量)基础知识","建筑工程",0]