[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1267668":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1267668,855,1,"单选题","当检查井内衔接的上、下游管渠的管底标高跌落差大于（ ）时，为消减水流速度，防止冲刷，在检查井内应有消能措施，这种检查井称为跌水井。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.5m",false,{"key":16,"text":17,"correct":18},"B","1m",true,{"key":20,"text":21,"correct":14},"C","1.5m",{"key":23,"text":24,"correct":14},"D","2m","检查井内衔接的上、下游管渠的管底标高跌落差大于1m时，为消减水流速度，防止冲刷，在检查井内应有消能措施，这种检查井称为跌水井。",{"id":6,"name":27,"category":28,"favorite":29},"(市政质量)基础知识","建筑工程",0]