[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1267651":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1267651,855,1,"单选题","钻孔灌注桩施工准备时，施工场地或工作平台的高度应考虑施工期间可能出现的高水位或潮水位，并比其高出（ ）m。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0.3~0.5",false,{"key":16,"text":17,"correct":18},"B","0.5~0.7",true,{"key":20,"text":21,"correct":14},"C","0.5~1.0",{"key":23,"text":24,"correct":14},"D","1.0~1.5","钻孔灌注桩施工准备时，施工场地或工作平台的高度应考虑施工期间可能出现的高水位或潮水位，并比其高出（B、0.5～O.7）m。",{"id":6,"name":27,"category":28,"favorite":29},"(市政质量)基础知识","建筑工程",0]