[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1267619":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1267619,855,1,"单选题","在河岸或水中修筑墩台时，为防止河水由基坑顶面浸人基坑，需要修筑围堰，围堰占用过水的断面不应超过原河床流水断面的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","20%",false,{"key":16,"text":17,"correct":18},"B","30%",true,{"key":20,"text":21,"correct":14},"C","40",{"key":23,"text":24,"correct":14},"D","50%","在河岸或水中修筑墩台时，为防止河水由基坑顶面浸人基坑，需要修筑围堰，围堰占用过水的断面不应超过原河床流水断面的30%。",{"id":6,"name":27,"category":28,"favorite":29},"(市政质量)基础知识","建筑工程",0]