[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1267590":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1267590,855,1,"单选题","湿软地基处理中，排水固结法由（ ）两部分共同组成。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","排水系统和气压系统",false,{"key":16,"text":17,"correct":14},"B","气压系统和泥浆系统",{"key":19,"text":20,"correct":21},"C","排水系统和堆载加压系统",true,{"key":23,"text":24,"correct":14},"D","泥浆系统和堆载加压系统","湿软地基处理中，排水固结法由排水系统和堆载加压系统两部分共同组成。",{"id":6,"name":27,"category":28,"favorite":29},"(市政质量)基础知识","建筑工程",0]