[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1267369":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1267369,855,1,"单选题","市政工程城区不开槽施工时，还必须识读设计咨询报告、（ ）和地下管线检测调查报告，以指导施工方案和施工监测方案编制。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","地质勘查报告",false,{"key":16,"text":17,"correct":14},"B","水文地质报告",{"key":19,"text":20,"correct":21},"C","工前检测报告",true,{"key":23,"text":24,"correct":14},"D","本区域同类项目后评估报告","市政工程城区不开槽施工时，还必须识读设计咨询报告、工前检测报告和地下管线检测调查报告，以指导施工方案和施工监测方案编制。",{"id":6,"name":27,"category":28,"favorite":29},"(市政质量)基础知识","建筑工程",0]