[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1267367":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1267367,855,1,"单选题","市政管道根据（ ）对纵向与横向采用不同的组合比例，以便显示管道的埋深与覆土。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","制图习惯",false,{"key":16,"text":17,"correct":18},"B","工程需要",true,{"key":20,"text":21,"correct":14},"C","图幅大小",{"key":23,"text":24,"correct":14},"D","开挖长高比值","市政管道根据工程需要对纵向与横向采用不同的组合比例，以便显示管道的埋深与覆土。",{"id":6,"name":27,"category":28,"favorite":29},"(市政质量)基础知识","建筑工程",0]