[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1267280":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":13,"analysis":19},1267280,854,3,"判断题","修正后的计划按程序文件规定经审核批准后才能执行。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",true,{"key":16,"text":17,"correct":18},"B","错误",false,"注意计划在执行中的修改，修正的起因有工程的变更，承包合同的修订、人员或物资的调整等。修正后的计划按程序文件规定经审核批准后才能执行。",{"id":6,"name":21,"category":22,"favorite":23},"(设备安装质量)专业管理实务 岗位知识","建筑工程",0]