[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1267022":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1267022,854,3,"判断题","单位工程质量验收时，要求质量控制资料基本齐全。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"单位工程完成后，施工单位应首先依据验收规范、设计图纸等组织有关人员进行自检，对检查结果进行评定并进行必要的整改。监理单位应根据《建设工程监理规范》的要求对工程进行竣工预验收。符合规定后由施工单位向建设单位提交工程竣工报告和完整的质量控制资料，申请建设单位组织竣工验收。",{"id":6,"name":21,"category":22,"favorite":23},"(设备安装质量)专业管理实务 岗位知识","建筑工程",0]