[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1267005":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1267005,854,3,"判断题","建筑工程竣工验收时，有关部门应按照设计单位的设计文件进行验收。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"工程的竣工验收由业主单位主持。会同设计、施工、设备供应单位及工程质量监督部门，对该项目是否符合规划设计要求以及建筑施工和设备安装质量进行全面检验，取得竣工合格资料、数据和凭证。",{"id":6,"name":21,"category":22,"favorite":23},"(设备安装质量)专业管理实务 岗位知识","建筑工程",0]