[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1266974":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1266974,854,2,"多选题","施工方项目管理的任务包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工安全管理",true,{"key":16,"text":17,"correct":18},"B","设计成本控制",false,{"key":20,"text":21,"correct":18},"C","项目进度控制",{"key":23,"text":24,"correct":14},"D","施工合同管理",{"key":26,"text":27,"correct":18},"E","项目质量控制","AD","施工方项目管理的任务：（1）施工安全管理；（2）施工成本控制；（3）施工进度控制；（4）施工质量控制；（5）施工合同管理；（6）施工信息管理；（7）与施工有关的组织与协调。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装质量)专业管理实务 岗位知识","建筑工程",0]