[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1266970":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1266970,854,2,"多选题","注意计划在执行的修正，修正的起因有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工程的变更",true,{"key":16,"text":17,"correct":14},"B","承包合同的修订",{"key":19,"text":20,"correct":21},"C","施工图纸的修改",false,{"key":23,"text":24,"correct":14},"D","人员或物资的调整",{"key":26,"text":27,"correct":21},"E","现场情况调查资料","ABD","注意计划在执行的修正，修正的起因有工程的变更，承包合同的修订、人员或物资的调整等。修正后的计划按程序文件规定经审核批准后才能执行。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装质量)专业管理实务 岗位知识","建筑工程",0]