[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1266958":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1266958,854,2,"多选题","（ ）等单位工程项目负责人应对本单位工程文件资料形成的全过程负总责。建设过程中工程文件资料的形成、收集、整理和审核应符合有关规定，签字并加盖相应的资格印章。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","建设",true,{"key":16,"text":17,"correct":14},"B","监理",{"key":19,"text":20,"correct":14},"C","勘察、设计",{"key":22,"text":23,"correct":14},"D","施工",{"key":25,"text":26,"correct":27},"E","材料供应",false,"ABCD","建设、监理、勘察、设计、施工等单位工程项目负责人应对本单位工程文件资料形成的全过程负总责。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装质量)专业管理实务 岗位知识","建筑工程",0]