[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1266947":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1266947,854,2,"多选题","分项工程质量计划编制步骤有：建立组织、制订计划、（ ）、按分工进行编写、（ ）、初审后改进、上级审核批复。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","确定负责人",false,{"key":16,"text":17,"correct":14},"B","跟踪检查",{"key":19,"text":20,"correct":21},"C","整理资料",true,{"key":23,"text":24,"correct":21},"D","编写组内部初审",{"key":26,"text":27,"correct":14},"E","归纳并分析合同文件","CD","分项工程质量计划编制步骤：①建立组织②修订计划③整理资料④按分工进行编写⑤编写组内部初审⑥初审后改进⑦上级审核批复见。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装质量)专业管理实务 岗位知识","建筑工程",0]