[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1266938":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1266938,854,2,"多选题","施工项目质量问题的原因有很多，（ ）是属于施工与管理不到位的原因。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","未经设计单位同意擅自修改设计",true,{"key":16,"text":17,"correct":18},"B","未搞清工程地质情况仓促开工",false,{"key":20,"text":21,"correct":18},"C","水泥安定性不良",{"key":23,"text":24,"correct":18},"D","采用不正确的结构方案",{"key":26,"text":27,"correct":14},"E","施工方案考虑不周，施工顺序颠倒","AE","施工项目质量问题的原因有很多，未经设计单位同意擅自修改设计、施工方案考虑不周，施工顺序颠倒是属于施工与管理不到位的原因。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装质量)专业管理实务 岗位知识","建筑工程",0]