[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1266934":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1266934,854,2,"多选题","质量管理发展的几个阶段（ ）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","事故检查阶段",false,{"key":16,"text":17,"correct":18},"B","统计质量管理阶段",true,{"key":20,"text":21,"correct":14},"C","做好事前质量控制的物资准备工作",{"key":23,"text":24,"correct":18},"D","质量管理与质量保证阶段",{"key":26,"text":27,"correct":18},"E","质量检查阶段","BDE","质量管理发展的几个阶段:质量检查阶段；统计质量管理阶段；全面质量管理阶段；质量管理与质量保证阶段。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装质量)专业管理实务 岗位知识","建筑工程",0]