[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1266932":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1266932,854,2,"多选题","施工组织计划的类型（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","施工组织总设计",true,{"key":16,"text":17,"correct":14},"B","施工组织设计",{"key":19,"text":20,"correct":21},"C","施工计划",false,{"key":23,"text":24,"correct":14},"D","施工方案",{"key":26,"text":27,"correct":21},"E","施工进度方案","ABD","施工组织计划的类型：施工组织总设计，一般以有多个单位工程组成的项目为对象；施工组织设计，一般以单位工程为对象；施工方案，以技术难度较大、采用新工艺或新材料的分部或分项工程为对象。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装质量)专业管理实务 岗位知识","建筑工程",0]