[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1266909":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1266909,854,2,"多选题","动态考核的特点（ ）",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","动设备受动力驱使而运转",true,{"key":16,"text":17,"correct":14},"B","管内有介质按要求而流动",{"key":19,"text":20,"correct":21},"C","线缆内电流不流通",false,{"key":23,"text":24,"correct":14},"D","线缆通电电气装置动作",{"key":26,"text":27,"correct":21},"E","线缆内电流易于控制","ABD","静态试验，是指已建成的工程实体，其动设备不运转、管内介质不流动、线缆内电流不流通的一种对承载能力的实验。动态考核，是指已建成的工程实体，其动设备受动力驱使而运转、管内有介质按要求而流动、线缆通电电气装置动作的一种功能性的考核，目的是鉴别其功能是否符合设计预计要求。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装质量)专业管理实务 岗位知识","建筑工程",0]