[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1266906":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1266906,854,2,"多选题","室外混凝土排水管道安装的工艺流程为：施工准备、（ ）、开挖沟槽、铺设基础、（ ）、管道与检查井等连接、（ ）、回填土、通水试验。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","测量放线",true,{"key":16,"text":17,"correct":14},"B","管道安装及连接",{"key":19,"text":20,"correct":21},"C","管道检漏",false,{"key":23,"text":24,"correct":21},"D","平整施工现场",{"key":26,"text":27,"correct":14},"E","灌水试验","ABE","室外混凝土排水管道安装的工艺流程为：施工准备、测量放线、开挖沟槽、铺设基础、管道安装及连接、管道与检查井等连接、灌水试验、回填土、通水试验。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装质量)专业管理实务 岗位知识","建筑工程",0]