[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1266903":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1266903,854,2,"多选题","以下关于设备和管道保温层的质量控制正确的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","保温层施工不应覆盖设备铭牌",true,{"key":16,"text":17,"correct":14},"B","每节管壳的绑扎不应少于2道",{"key":19,"text":20,"correct":21},"C","管道上的阀门、法兰等需经常维护的部位，保温层不能做成可拆卸式结构",false,{"key":23,"text":24,"correct":14},"D","管道上的阀门、法兰等需经常维护的部位，保温层可做成可拆卸式结构",{"key":26,"text":27,"correct":14},"E","保温层的接触缝要用同样材料的胶泥勾缝","ABDE","保温层施工不应覆盖设备铭牌；每节管壳的绑扎不应少于2道；保温层的接触缝要用同样材料的胶泥勾缝；管道上的阀门、法兰等需经常维护的部位，保温层要做成可拆卸式结构。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装质量)专业管理实务 岗位知识","建筑工程",0]