[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1266849":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1266849,854,2,"多选题","通风与空调工程系统无生产负荷的联合试运转及调试，应在制冷设备和通风与空调设备单机试运转合格后进行。空调系统带冷（热）源的正常联合试运转不应少于（ ）通风、除尘系统的连续试运转不应少于（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","2h",true,{"key":16,"text":17,"correct":18},"B","1h",false,{"key":20,"text":21,"correct":18},"C","24h",{"key":23,"text":24,"correct":18},"D","10h",{"key":26,"text":27,"correct":14},"E","8h","AE","",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装质量)专业管理实务 岗位知识","建筑工程",0]