[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1266845":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1266845,854,2,"多选题","通风与空调工程安装完毕，必须进行系统的测定和调整（简称调试）。系统调试应包括下列项目：（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","设备单机试运转及调试",true,{"key":16,"text":17,"correct":14},"B","系统无生产负荷下的联合试运转及调试",{"key":19,"text":20,"correct":21},"C","综合效能的测定与调整",false,{"key":23,"text":24,"correct":21},"D","有负荷下的联合试运转",{"key":26,"text":27,"correct":21},"E","无生产负荷的测定与调整","AB","《通风与空调工程施工质量验收规范》第11.2.1条规定，通风与空调工程安装完毕，必须进行系统的测定和调整（简称调试）。系统调试应包括下列项目：设备单机试运转及调试、系统无生产负荷下的联合试运转及调试。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装质量)专业管理实务 岗位知识","建筑工程",0]