[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1266752":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1266752,854,2,"多选题","分部（子分部）工程验收合格的规定包括（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","分部（子分部）工程所含分项工程的质量均应验收合格",true,{"key":16,"text":17,"correct":14},"B","质量控制资料应完整",{"key":19,"text":20,"correct":14},"C","地基与基础、主体结构等分部工程有关安全及功能的检测和抽样检测结果应符合有关规定",{"key":22,"text":23,"correct":14},"D","观感质量应符合要求",{"key":25,"text":26,"correct":27},"E","人员资料应完整",false,"ABCD","分部（子分部）工程验收合格的规定包括1）分部（子分部）工程所含分项工程的质量均应验收合格2）质量控制资料应完整3）地基与基础、主体结构、设备安装等分部工程有关安全及功能的检测和抽样检测结果应符合有关规定4）感官质量应符合要求。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装质量)专业管理实务 岗位知识","建筑工程",0]