[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1266742":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1266742,854,2,"多选题","设备验收准备的内容包括：（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","决定参与验收的人员",true,{"key":16,"text":17,"correct":14},"B","收集采购协议或合同、质量标准等技术资料",{"key":19,"text":20,"correct":14},"C","配备相应的检测和计量工具",{"key":22,"text":23,"correct":24},"D","准备供货源头资料",false,{"key":26,"text":27,"correct":24},"E","项目经理的签字确认","ABC","设备验收准备的内容包括：决定参与验收的人员；收集采购协议或合同、质量标准等技术资料；配备相应的检测和计量工具。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装质量)专业管理实务 岗位知识","建筑工程",0]