[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1266724":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1266724,854,2,"多选题","建设单位收到工程竣工报告后，应由建设单位项目负责人组织（ ）等单位项目负责人进行单位工程验收。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","监理",true,{"key":16,"text":17,"correct":14},"B","施工",{"key":19,"text":20,"correct":14},"C","设计",{"key":22,"text":23,"correct":14},"D","勘察",{"key":25,"text":26,"correct":27},"E","检测",false,"ABCD","建设单位收到工程竣工报告后，应由建设单位项目负责人组织监理、施工、设计、勘察等单位项目负责人进行单位工程验收。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装质量)专业管理实务 岗位知识","建筑工程",0]