[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1266720":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1266720,854,2,"多选题","备案管理的相关规定中规定竣工验收备案提交的文件包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工程竣工验收备案表",true,{"key":16,"text":17,"correct":14},"B","工程竣工验收报告",{"key":19,"text":20,"correct":21},"C","工程竣工检查报告",false,{"key":23,"text":24,"correct":21},"D","工程验收评审报告",{"key":26,"text":27,"correct":21},"E","工程验收报审表","AB","备案管理的相关规定中规定竣工验收备案提交的文件包括1）工程竣工验收备案表2）工程竣工验收报告。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装质量)专业管理实务 岗位知识","建筑工程",0]