[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1266695":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1266695,854,1,"单选题","不属于事中质量控制的具体措施是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","控制施工有重点",true,{"key":16,"text":17,"correct":18},"B","质量处理有复查",false,{"key":20,"text":21,"correct":18},"C","材料代换有制度",{"key":23,"text":24,"correct":18},"D","设计变更有手续","事中质量控制的策略是：全面控制施工过程，重点控制工序质量。具体措施是：工序交接有对策，质量预控有对策，施工项目有方案，技术措施有交底，图纸会审有记录，设备材料有检验，隐蔽工程有验收，计量器具校正有复核，设计变更有手续，材料代换有制度，质量处理有复查，成品保护有措施，行使质控有否决，质量文件有档案。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装质量)专业管理实务 岗位知识","建筑工程",0]