[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1266693":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1266693,854,1,"单选题","不属于试运行中使用的仪器、仪表的要求（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","符合试运行中检测工作要求",false,{"key":16,"text":17,"correct":14},"B","精度等级、量程等技术指标符合被测量的需要",{"key":19,"text":20,"correct":21},"C","试运行所需的电力、供水、供气均接入到位",true,{"key":23,"text":24,"correct":14},"D","显示部分如指针或数字清晰可辨","试运行中使用的仪器、仪表的要求：符合试运行中检测工作的需要；精度等级、量程等技术指标符合被测量的需要；必须经过检定合格，有标识，在检定周期内；外观检查部件齐全，无明显锈蚀和受潮现象；显示部分如指针或数字清晰可辨。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装质量)专业管理实务 岗位知识","建筑工程",0]