[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1266679":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1266679,854,1,"单选题","施工企业首次采用“四新”技术，需要在质量计划中编写技术要求和（ ）两大部分。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","设计要求",false,{"key":16,"text":17,"correct":14},"B","施工要求",{"key":19,"text":20,"correct":14},"C","验收要求",{"key":22,"text":23,"correct":24},"D","管理要求",true,"如施工企业无合适的工艺标准等技术文件或首次采用“四新”技术，则在质量计划中要编写技术要求和管理要求两大部分。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装质量)专业管理实务 岗位知识","建筑工程",0]