[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1266647":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1266647,854,1,"单选题","设备和管道的保温层厚度大于（ ）mm时，应分两层或多层逐层施工。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","240",false,{"key":16,"text":17,"correct":14},"B","360",{"key":19,"text":20,"correct":21},"C","100",true,{"key":23,"text":24,"correct":14},"D","120","设备和管道的保温层厚度大于100mm时，应分两层或多层逐层施工，同层要错缝，异层要压缝。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装质量)专业管理实务 岗位知识","建筑工程",0]