[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1266644":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1266644,854,1,"单选题","施工准备阶段的质量控制，属于（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","事前控制",true,{"key":16,"text":17,"correct":18},"B","事中控制",false,{"key":20,"text":21,"correct":18},"C","事后控制",{"key":23,"text":24,"correct":18},"D","实时控制","事前控制指是指在正式施工前进行的质量控制，其控制重点是做好施工准备工作，且施工准备工作要贯穿于施工全过程中。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装质量)专业管理实务 岗位知识","建筑工程",0]