[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1266634":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1266634,854,1,"单选题","设备安装工程的施工试验分类从时间阶段划分（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工准备阶段的施工试验",true,{"key":16,"text":17,"correct":18},"B","静态试验和施工准备阶段的施工试验",false,{"key":20,"text":21,"correct":18},"C","动态考核和施工准备阶段的施工试验",{"key":23,"text":24,"correct":18},"D","静态试验和动态考核","设备安装的施工试验分类：从时间阶段划分，可分为施工准备阶段的施工试验；从试验状态划分，设备安装工程试验划分为静态试验和动态考核两类。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装质量)专业管理实务 岗位知识","建筑工程",0]