[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1266540":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1266540,854,1,"单选题","空调系统试压：在各分区管道与系统主、干管全部连通后，对整个系统的管道进行系统的试压。试验压力以最低点的压力为准，但最低点的压力不得超过管道与组成件的承受压力。压力试验升至试验压力后，稳压10min，压力下降不得大于（ ）MPa，再将系统压力降至工作压力，外观检查无渗漏为合格。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","0.05",false,{"key":16,"text":17,"correct":14},"B","0.03",{"key":19,"text":20,"correct":21},"C","0.02",true,{"key":23,"text":24,"correct":14},"D","0.01","",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装质量)专业管理实务 岗位知识","建筑工程",0]