[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1266518":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1266518,854,1,"单选题","某总承包单位将综合楼的通风空调工程分包给某安装单位，工程内容有风系统、水系统和冷热（媒）设备。通风空调设备安装完工后，在总承包单位的配合下，安装单位对通风空调的风系统、水系统和冷热（媒）系统进行了系统调试。调试人员在单机试运行合格后，又对各风口进行测定与调整及其他内容的调试，在全部数据达到设计要求后，在夏季做了带冷源的试运转，并通过竣工验收。综合楼正式使用后，又对通风空调工程进行了带负荷综合效能实验与调整。试回答下列问题： 风管的风量采用（ ）进行测量",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","毕托管-微压计",true,{"key":16,"text":17,"correct":18},"B","转子流量计",false,{"key":20,"text":21,"correct":18},"C","叶轮风速仪",{"key":23,"text":24,"correct":18},"D","风速流量计","",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装质量)专业管理实务 岗位知识","建筑工程",0]