[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1266394":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1266394,854,1,"单选题","自动喷水灭火系统水压强度试验的测试点应设在系统管网的最低点。对管网注水时，应将管网内的空气排净，并应缓慢升压；达到试验压力后，稳压30min后，管网应无泄漏、无变形，且压力降不应大于（ ）MPa。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","0.02",false,{"key":16,"text":17,"correct":14},"B","0.03",{"key":19,"text":20,"correct":14},"C","0.04",{"key":22,"text":23,"correct":24},"D","0.05",true,"",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装质量)专业管理实务 岗位知识","建筑工程",0]