[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1266382":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1266382,854,1,"单选题","室内给水系统安装的工艺流程正确顺序是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","孔洞预留、埋件→支管安装→立管安装→干管安装→水压试验→管道防腐和保温→管道冲洗→通水试验",false,{"key":16,"text":17,"correct":18},"B","孔洞预留、埋件→干管安装→立管安装→支管安装→水压试验→管道防腐和保温→管道冲洗→通水试验",true,{"key":20,"text":21,"correct":14},"C","孔洞预留、埋件→支管安装→立管安装→干管安装→管道防腐和保温→水压试验→管道冲洗→通水试验",{"key":23,"text":24,"correct":14},"D","孔洞预留、埋件→干管安装→立管安装→支管安装→管道防腐和保温→水压试验→管道冲洗→通水试验","工艺流程：孔洞预留、埋件→预制加工→干管（套管）安装→立管（套管）安装→支管安装→水压试验→管道防腐和保温→管道冲洗（消毒）→通水试验。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装质量)专业管理实务 岗位知识","建筑工程",0]