[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1266374":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1266374,854,1,"单选题","增压设备和水箱安装的工艺流程，正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","安装准备→基础验收→吊装就位→设备开箱检查→找平找正→配管安装→试运转",false,{"key":16,"text":17,"correct":14},"B","安装准备→基础验收→设备开箱检查→找平找正→吊装就位→配管安装→试运转",{"key":19,"text":20,"correct":21},"C","安装准备→基础验收→设备开箱检查→吊装就位→找平找正→配管安装→试运转",true,{"key":23,"text":24,"correct":14},"D","安装准备→基础验收→设备开箱检查→吊装就位→配管安装→找平找正→试运转","工艺流程：安装准备→基础验收→设备开箱检查→吊装就位→找平找正→配管安装→试运转。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装质量)专业管理实务 岗位知识","建筑工程",0]