[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1266346":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1266346,854,1,"单选题","某行政办公楼2012年3月主体工程施工完毕，开始进行给水排水管道安装施工，承包单位合理安排施工，严格把好质量关，2012年7月底工程顺利通过竣工验收并投入使用，请问管道施工时应注意哪些问题。 给水管道安装顺序（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","安装→试压→保温→消毒→冲洗",true,{"key":16,"text":17,"correct":18},"B","安装→保温→试压→消毒→冲洗",false,{"key":20,"text":21,"correct":18},"C","安装→试压→消毒→冲洗→保温",{"key":23,"text":24,"correct":18},"D","安装→保温→试压→冲洗→消毒","",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装质量)专业管理实务 岗位知识","建筑工程",0]