[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1266310":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1266310,854,1,"单选题","单位工程的观感质量应由验收人员通过现场检查，并应（ ）确认。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","监理单位",false,{"key":16,"text":17,"correct":14},"B","施工单位",{"key":19,"text":20,"correct":14},"C","建设单位",{"key":22,"text":23,"correct":24},"D","共同",true,"单位工程的观感质量应由验收人员通过现场检查，并应共同确认。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装质量)专业管理实务 岗位知识","建筑工程",0]