[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1266275":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1266275,854,1,"单选题","现行的《建筑给水排水及采暖工程施工质量验收规范》GB50242-2002中要求各种承压管道系统和设备应做（ ），非承压管道系统和设备应做（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","水压实验，满水实验",false,{"key":16,"text":17,"correct":18},"B","水压实验，灌水实验",true,{"key":20,"text":21,"correct":14},"C","满水实验，灌水实验",{"key":23,"text":24,"correct":14},"D","灌水实验，满水实验","各种承压管道系统和设备应做水压实验，非承压管道系统和设备应做灌水试验。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装质量)专业管理实务 岗位知识","建筑工程",0]