[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1265983":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1265983,853,1,"单选题","根据机电工程注册建造师签章文件类别要求，下列选项中属于成本费用管理文件的是（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程设备采购总计划表",false,{"key":16,"text":17,"correct":14},"B","工程一切保险委托书",{"key":19,"text":20,"correct":14},"C","现场临时用电申请书",{"key":22,"text":23,"correct":24},"D","工程人身保险申报表",true,"机电工程注册建造师填写签章文件中成本费用管理文件包括：工程款支付报告；工程变更费用报告；费用索赔申请表；费用变更申请表；月工程进度款报告；工程经济纠纷处理备案表；阶段经济分析的审核；债权债务总表；有关的工程经济纠纷处理；竣工结算申报表；工程保险（人身、设备、运输等）申报表；工程结算审计表。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装质量)基础知识","建筑工程",0]