[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1265964":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1265964,853,1,"单选题","灌水试验的检验方法是，灌水到满水15min，水面下降后再灌满观察（ ），液面不降，室内排水管道的接口无渗漏为合格。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1min",false,{"key":16,"text":17,"correct":14},"B","3min",{"key":19,"text":20,"correct":21},"C","5min",true,{"key":23,"text":24,"correct":14},"D","8min","灌水试验的检验方法是，灌水到满水15min，水面下降后再灌满观察5min，液面不降，室内排水管道的接口无渗漏为合格。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装质量)基础知识","建筑工程",0]