[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1265963":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1265963,853,1,"单选题","空调系统带冷（热）源的连续试运行时间应不少于（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2h",false,{"key":16,"text":17,"correct":18},"B","8h",true,{"key":20,"text":21,"correct":14},"C","12h",{"key":23,"text":24,"correct":14},"D","24h","通风与空调系统无生产负荷的联合试运行及调试，应在设备单机试运转合格后进行。通风系统的连续试运行应不少2h，空璃系统带冷热）源的连续试运行应不少于8h。联合试运行及调试不在制冷期或供暖期时，仅做不带冷（热）原的试运行及调试，并在第一个制冷期或供暖期内补作。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装质量)基础知识","建筑工程",0]