[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1265960":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1265960,853,1,"单选题","电力电容器安装工序中电容器二次搬运的紧后工序是",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","连线",false,{"key":16,"text":17,"correct":18},"B","电容器安装",true,{"key":20,"text":21,"correct":14},"C","送电前检查",{"key":23,"text":24,"correct":14},"D","送电运行验收","电力电容器安装工序：开箱清点→设备基础制作安装或框架制作安装→电容器二次搬运→电容器安装→连线→送电前检查→送电运行验收。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装质量)基础知识","建筑工程",0]