[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1265943":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1265943,853,1,"单选题","室内电缆敷设程序中电缆管加工与敷设的紧后工序是",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","电缆牌制作",true,{"key":16,"text":17,"correct":18},"B","电缆电气试验",false,{"key":20,"text":21,"correct":18},"C","电缆沟接地线安装",{"key":23,"text":24,"correct":18},"D","电缆两端电气设备安装","电缆敷设程序：电缆架配置与安装→电缆管加工与敷设→电缆牌制作→电缆电气试验→电缆沟接地线安装→电缆两端电气设备安装→电缆敷设→电缆挂牌。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装质量)基础知识","建筑工程",0]