[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1265898":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1265898,853,1,"单选题","工程开工前，项目部编制《计量检测设备配备计划书》的依据通常不包括（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工组织设计",false,{"key":16,"text":17,"correct":14},"B","施工方案",{"key":19,"text":20,"correct":21},"C","安全计划",true,{"key":23,"text":24,"correct":14},"D","项目质量计划","施工现场计量器具的使用要求之一是：工程开工前，项目部应根据项目质量计划、施工组襄。对检测设备的精度要求和生产需要，编制’《计量检测设备配备计划书》。建立项目部计量器具的目录和检定周期台账档案。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装质量)基础知识","建筑工程",0]