[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1265875":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1265875,853,1,"单选题","电气交接试验的目的是判定工程是否符合要求，是否（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","满足设计要求",false,{"key":16,"text":17,"correct":14},"B","符合制造标准",{"key":19,"text":20,"correct":14},"C","达到山力要求",{"key":22,"text":23,"correct":24},"D","可以投入运行",true,"交接试验是建筑电气工程安装结束后全面检测测试的重要工序，以判定工程是否符合要求，是否可以通电投入运行。只有交接试验合格，建筑电气工程才能受电试运行。",{"id":6,"name":27,"category":28,"favorite":29},"(设备安装质量)基础知识","建筑工程",0]